Registration Number (HPBC) 174
Design Checking Duration
Under Constructed Duration
Developer Shwe Oak Khai Co.,Ltd.
Storey 2B + (17 Storeyed and 24 Storeyed)
Building Type Residential
Address No- 4/A, Hlaing River Road, Insein Township.
Project Status

Design Status

Project Status
Architecture 1. Recommended for Structure, Electrical, Water Supply and Sanitation and ACMV.
Structure 1. Presenting sub-structure design.(11.9.15)
2.(UPLT) Pile Load Test recommended. (5.10.15)
3. (WPLT+DLT) Pile Load Test recommended.( 8.10.15)
4. DE recommended.(11.11.15)
5. Piling recommended. (31.12.15)
6.Foundation recommended. (21.3.16)
7. Recommend Superstructure Design. (1.9.16)
Electrical 1. Recommended on ( 1.9.2016).
ACMV 1. Recommended on ( 1.9.2016).
Water Supply & Sanitation 1. Recommended on ( 12.9.2016).