Registration Number (HPBC) | 206 |
Design Checking Duration | |
Under Constructed Duration | |
Developer | Royal Lotus |
Storey | 9 |
Building Type | |
Address | Pathein |
Project Status |
Project Status | |
Architecture | 1. Recommended for Structure. (26.12.16) |
Structure | 1. Recommended for Structure. (26.12.16) |
Electrical | 1. Recommended on ( 29.1.2018). |
ACMV | 1. Recommended on ( 29.1.2018). |
Water and Sanitation | 1. Presentation at (28.8.17) 2. Comment sent on (4.9.17). 3. Submit Revised (1) sets on (2.10.17). 4. Discuss with company on (10.10.17). 5. Send 3rd times reminder on (15.1.18). 6. Discuss with company on (16.1.18). 7. Submit Revised (1) sets on (18.1.18). 8. Discuss with company on (2.2.18) and (8.2.18). 9. Submit Revised (1) sets on (12.3.18) . 10. Discuss with company by phone on (22.3.18). 11. Waiting for comment’s reply. 12. Reminder sent on (21.6.18) |